Building Beer – Week 11

30
Jul
2015

WEEK 11

7f5ffea4-1486-4997-9dfd-77707be3ed83

While the guys from DG Masonry formed and poured out the basement walls, Mike and his crew from Homer Iron Works and a crew from Complete Construction Concepts spent most of the day unloading 13 tractor loads of metal building components. Once the concrete floors are poured, these metal components will be bolted together to form the frame of the building.

 

Here is a video of the building being unloaded through the all the encompassing view of our trusty Go Pro…

 

 

adae32e2-9d70-43c2-83d3-97ba39d18316 8f97a9ee-72fd-491f-bcec-d9a445348b20

 

351d8ca2-e5d0-4160-967f-1aa7768d6886

Forms are constructed for the basement walls….

86ad7e6d-ec03-48be-9f3f-a972054a12e5

a pump truck pumps concrete into the basement wall forms…

feeb4797-271f-47ff-b942-6a067ff524fd

¬†Back filling and compaction around the piers…

97bff876-f88b-494a-9a6e-00198c826a14

The basement walls are poured and the concrete guys are out of here for a few weeks while Halco MEP’s, the company installing all of our plumbing and electrical utilities, begins work on the plumbing and electrical being installed underneath the concrete floors.

We are getting into the heat now and continue to hope for dry weather as things move forward!