BUILDING BEER – WEEK 15

22
Aug
2015

WEEK 15

198ab3e3-a810-4881-9923-0bd040026417-1

The excavators have continued to add top soil and seed the areas that are finished, the picture above is the beginnings of our backyard which has been aptly designed for epic corn hole tournaments.

The plumbers and electricians have been hard at work getting utilities in underground before the masons come back and pour the concrete floor, hopefully at the end of the week. The pictures below show underground piping in the kitchen area,

e9cef086-a1b7-4c4b-b115-4fae13c14d6a

940b88bb-f580-4b31-98d9-56fcab5377cd-1 fd177e57-aa26-4b91-8b0c-b4f48ff753c5

Basement walls are complete and the plumbers are putting in drain piping.

662afdb9-82f5-4882-b65c-c528825f020b

Excavation for our process waste tanks. These tanks will equalize the waste water created during the brewing process, also giving us the opportunity to treat it before it heads down stream if need be.

1db09f09-60c8-41d8-8259-33b02fc0d57b 46cc7ab7-9442-4ec6-88e5-4b6d3e66c045

 

The process waste tanks were set with a crane and the plumbers began to pipe them together.