Are you over 21?

*This uses cookies.

Get email updates about upcoming Empire events in your area!


What’s Happening

Building Beer – Week 20

WEEK 20

Steel Structure Continues

7b4afaac-5c6d-455c-b816-1d316a78c9d8

The guys from Homer Iron Works have been putting in long days and the steel structure is going up quite nicely.

Here are a few pictures of the steel progress.

17e73a6d-23aa-4db1-8eca-5de010820b42

93c67782-d903-4c9b-a097-5317bc0f1dfc

9814e265-451d-4369-b047-e53545fafa62

dc68bc12-9e0b-4c64-a26c-2dbcc0a5f311

The basement floor is poured, ready for the sour beers.

7771b6b8-8f52-4627-a599-d7de412bcfaf

ae5d790b-b4b7-4754-bf87-ca92de59061f

The main structure is mostly complete and the tasting room / office section has begun to go up.

Building Beer – Week 17

WEEK 17

Concrete’s down, steel’s up!1116d4a1-df5b-4038-a3fe-803b10bfa73b

Steel’s here and the guys from Homer Iron Works are taking advantage of the great weather and moving fast!

The steel couldn’t go up until DG Masonry got all of the concrete floors poured. Click here for footage of the floors going down.

2966e797-7c15-4d40-940a-e1d1e44be307 d4d81824-d01d-435b-a8a9-3eb7bf2a4fad

65f0b862-5429-4daa-8642-374a6c5e42fc

Installation of the floor joists over the basement began.

3e076e12-0002-49c9-8861-efa64f019c79 955eb88c-bed5-4e22-9ae4-9143e165d6ea

Oh yeah, and our hop poles arrived! Wayne Law from Law Logging delivered us the first load of great looking poles that will make up almost 3 acres of hop yard. We sealed the butts and will hopefully get them in the ground in the next 30 days.

BUILDING BEER – WEEK 15

WEEK 15

198ab3e3-a810-4881-9923-0bd040026417-1

The excavators have continued to add top soil and seed the areas that are finished, the picture above is the beginnings of our backyard which has been aptly designed for epic corn hole tournaments.

The plumbers and electricians have been hard at work getting utilities in underground before the masons come back and pour the concrete floor, hopefully at the end of the week. The pictures below show underground piping in the kitchen area,

e9cef086-a1b7-4c4b-b115-4fae13c14d6a

940b88bb-f580-4b31-98d9-56fcab5377cd-1 fd177e57-aa26-4b91-8b0c-b4f48ff753c5

Basement walls are complete and the plumbers are putting in drain piping.

662afdb9-82f5-4882-b65c-c528825f020b

Excavation for our process waste tanks. These tanks will equalize the waste water created during the brewing process, also giving us the opportunity to treat it before it heads down stream if need be.

1db09f09-60c8-41d8-8259-33b02fc0d57b 46cc7ab7-9442-4ec6-88e5-4b6d3e66c045

 

The process waste tanks were set with a crane and the plumbers began to pipe them together.

 

 

 

 

Building Beer – Week 11

WEEK 11

7f5ffea4-1486-4997-9dfd-77707be3ed83

While the guys from DG Masonry formed and poured out the basement walls, Mike and his crew from Homer Iron Works and a crew from Complete Construction Concepts spent most of the day unloading 13 tractor loads of metal building components. Once the concrete floors are poured, these metal components will be bolted together to form the frame of the building.

 

Here is a video of the building being unloaded through the all the encompassing view of our trusty Go Pro…

 

 

adae32e2-9d70-43c2-83d3-97ba39d18316 8f97a9ee-72fd-491f-bcec-d9a445348b20

 

351d8ca2-e5d0-4160-967f-1aa7768d6886

Forms are constructed for the basement walls….

86ad7e6d-ec03-48be-9f3f-a972054a12e5

a pump truck pumps concrete into the basement wall forms…

feeb4797-271f-47ff-b942-6a067ff524fd

 Back filling and compaction around the piers…

97bff876-f88b-494a-9a6e-00198c826a14

The basement walls are poured and the concrete guys are out of here for a few weeks while Halco MEP’s, the company installing all of our plumbing and electrical utilities, begins work on the plumbing and electrical being installed underneath the concrete floors.

We are getting into the heat now and continue to hope for dry weather as things move forward!

Building Beer – Week 7

WEEK 7

fb31d556-0490-4308-b5ac-b69bf7a05518

 Concrete has arrived!

The team on site has grown to include DG Masonry who poured footers from the piers last week, and weather permitting will continue to pour piers and footers for the basement walls.

But first, enjoy a ride from the view of our dozer cam! The guys from Burrell’s Excavation were cool enough to take the Go Pro along as they finished the grading at the front of the property.

42b5ed0f-24ef-4f17-b7d2-4afa3326c884

2c2468d4-e773-48ca-92f2-5cde90bc98a4        cdb811b5-26bb-4f9a-89e5-b604d937ae2a

 

4ce2649b-4bba-44ff-9346-5dd3cb3195a0

Excavation is complete on the cellar and this week they will put in footers and walls.

 

d10deaa4-1e32-4cd7-8f0a-b9376bd00719

Meet Larry, the construction dog! Larry tags along with David Gillis, owner of DG Masonry, and keeps everyone on site in line.

Building Beer – Week 5

WEEK 5

2cc0e0c0-5d0f-4898-8d9e-dd68c2405713

More of the same this past week, the guys did what they could in between rain storms, making good progress building up the road by bringing in loads of gravel from a local quarry.

0f695239-2796-49b1-b1d2-43fc8762e7b6 a38234ec-b92b-4bcb-b259-249ff4f9301f 2cc0e0c0-5d0f-4898-8d9e-dd68c2405713 b55f9526-09e9-4e31-adfb-aab44031f2be 29964676-ceea-41ba-923d-c91b1d08cb07 2c90f32f-c008-40f9-9142-1efb74324220 4fede329-27ba-4f5f-bdb7-8b6ece0d0ba5 fe033a6a-c2cf-4633-9039-db2edbd51fce

Check out our time-lapse video of a days excavating work!

Building Beer – Week 3

WEEK 3

d776be11-f340-4e7b-b75d-3c41dd8994c8

Despite the rain early last week, the crew was able to start working on Wednesday to install the drivewat entrance off Route 13!

1ee5b6bf-2623-4b72-83b0-ab5cdd69a8e6

e36119fc-b874-434c-affb-def7a4926ef4

Installation of the driveway entry.

 

acd5b4d5-dd6e-4bcc-9878-a99ab4d3df19

Excavation on the basement and back patio area has started.

a8e70a90-a6e4-4f69-877b-357470bae16d

Fill from the basement area was dumped and spread to continue building the roadway.

0345abbb-e115-45e2-808e-9c0ed22c7345

Friday morning they dropped off another bulldozer and began using some of the fill from the basement for grading out the building pad.

 

 

Building Beer – Week 2

Week 2

61bc5802-4f30-4e06-b827-a6812bfaf46c

Construction Continues

Another week of beautiful weather is behind us and this kept the earth moving on site at the Empire Farm Brewery. Unfortunately the rain that was much needed for our gardens put construction on hold for a few days…

Last week the guys continued to strip and pile top soil, pull stumps, prep the pad and work on the road. The road presented a problem with a low wet spot they couldn’t compact, but after a dozen loads of cobble stones they finally got it filled in and the road in place.

54031edb-31ec-4676-8508-1502146c3f9f

A Week of pumping water out of the wet area yielded little progress.

3ec50049-2c77-4a0d-b9d9-03cc47d0843e

The road is in place for construction vehicles to access the building pad.

 

 

 

 

 

 

 

 

 

 

 

fc4f0c0a-fcfb-43c0-a06b-c9ebe24a1cfb

Heavy rain over the weekend presented it’s fair share of challenges.

87236937-c6d1-459b-b5e0-bd6f77cda01c

A dozen loads of cobbles were delivered to fill in the wet area and give the sub base some substance.

 

 

 

 

 

 

 

 

 

 

 

 

DSC_1059

DSC_1035

DSC_1038

DSC_1057

Empire Farm Brewery Groundbreaking – Cazenovia, New York

Empire Farm Brewery Groundbreaking

May 8, 2015

earth

The Empire Farm Brewery broke ground today, in Cazenovia, New York where the 60 BBl brewing/ tasting room facility will soon begin construction. Slated to open in the 4th Quarter of 2015, the Empire Farm Brewery is poised to be the largest Farm Brewery in New York State.  The site will be developed for both educational and beer production purposes.  The property will also grow hops, lavender, vegetables, herbs, and fruits for use in the brewing process and to support the needs of Empire Brewing Company.  An apiary is being developed on the west end of the property to produce hop and lavender honey, which will be used in the brewing process.

farm

The objective of the Empire Farm Brewery is to expand the existing brewing facility and agricultural component of Empire Brewing Company to a stand-alone manufacturing and agritourism facility located on Route 13 in Cazenovia, NY.  Beer manufactured here will be packaged in kegs, bottles and cans for regional and international distribution.  There is also a gift shop and restaurant component that will be open Wednesday through Sunday.  Brewery and beer garden tours will also be available during weekends.  The project will capture the interest of the brewing community, farmers, educators, hop historians, beer geeks, and industries interested in learning from our green business practices.firkinladies

The new brewery is being manufactured by Feldmeier Equipment, Inc.  The system will utilize locally grown feedstock (hops, grains, and other locally sourced products), providing a direct benefit to farmers in Central New York while simultaneously decreasing the company’s carbon footprint.  We will buy NYS manufactured and grown products whenever feasible.  The project construction and manufacturing process will also be designed as “green”.  The company proposes to construct an environmentally friendly facility using green building materials and introduce energy efficient technologies.  The company’s attention to “green” manufacturing will only further serve to differentiate our products and make them uniquely New York.

glass

We are approved for Start-Up NY. Start-Up NY is Governor Cuomo’s groundbreaking initiative, is creating tax-free zones across the state for new and expanding businesses.  In partnership with Morrisville State College, Empire Brewing Company will expand into Empire Farm Brewery which will operate tax-free for 10-years. The College has implemented a new Brewing Studies program and will work directly with Empire’s team to develop, implement and manage the program while educating the students of Morrisville State College with first hand practical business experience with a large scale production brewery.

Cameras

The design of the Empire Farm Brewery incorporates the historical significance of Madison County’s rich hop growing past while architecturally complimenting the natural elements of the area.  The design is understated and reminiscent of a classic Upstate New York farm while paying homage to local hop barn architecture.  With clarity the aim and renewable material and ambient lighting the accent, it is our goal to create a warm and inviting environment that blend with our landscape and our community.  Kurt Ofer, of Altonview Architects, has designed the facility. Mr. Ofer is credited for the architectural design of Brewery Ommegang in Cooperstown, NY, and is working directly with Empire, SUNY ESF, and other consultants to produce a world-class brewery. The tasting room, retail space, restaurant, cellar and office are being designed by Ashley Freund Interiors. An early 19th century barns have been decommissioned for reuse in the tasting room. And bricks for Syracuse’s original Haberle Brewery will be incorporated throughout the facility.

Earth Day 2015 with OCRRA

Team Empire

In 2014, 5,500 OCRRA earth day volunteers collected more than 99,000 pounds of litter. In the two decades since OCRRA started the earth day clean up program, over 2,008,880 pounds of trash have been collected from our neighborhood communities! This year, Empire put out the call for earth day volunteers. Staff, friends and family responded with enthusiasm, and our own Empire team of all ages spent a sunny Saturday cleaning up the inner harbor in downtown Syracuse.

 

EarthDay_2015_groupII

DSC_0935

DSC_0952

DSC_0982

 

FullSizeRenderDSC_0948

EarthDay_2015_groupI